KISKI VALLEY WATER POLLUTION CONTROL AUTHORITY

PLANT EXPANSION PROJECT

PROJECT BASIS

DEBT SERVICE CALCULATION

The Kiski Valley Water Pollution Control Authority (KVWPCA) plant initiated construction in 1972 and began receiving wastewater from thirteen (13) communities in 1975. These communities are: Borough of Apollo, Borough of Leechburg, Borough of North Apollo, Gilpin Township, Kiskiminetas Township and Parks Township in Armstrong County and Allegheny Township, Borough of East Vandergrift, Borough of Hyde Park, Borough of Oklahoma, Borough of Vandergrift, Borough of West Leechburg and Washington Township in Westmoreland County. The initial construction included installation of sewers for conveyance of wastewater and storm water from these communities to the treatment plant and included Combined Sewer Overflows (CSOs). The CSOs discharge untreated wastewater and storm water to the environment in the event that the flow volume from the combined streams exceeds the hydraulic capacity of the conveyance piping or treatment facility.        

The treatment facility, as originally constructed, has an average daily design hydraulic capacity of 7.0 Million Gallons per Day (MGD) with the capacity to accept and treat peak flows up to 19.1 MGD. The existing KVWPCA wastewater treatment facility provided preliminary, primary and secondary treatment along with disinfection prior to being discharged to the Kiskiminetas River under the terms of NPDES Permit Number PA0027626. This permit also identifies twenty nine (29) CSO outfalls and imposes specific requirements for the management and control of the CSOs.

One of the CSO control requirements specified in the NPDES Permit is submittal of a Long Term Control Plan (LTCP) for controlling CSOs to the Pennsylvania Department of Environmental Protection (PADEP) and implementation of the LTCP plan upon approval. According to Environmental Protection Agency (EPA) policy, development of a LTCP for controlling CSOs can utilize one of two approaches; a “demonstration approach” which shows that the plan is adequate to meet water quality standards in the surface water body receiving the CSOs, or a “presumption approach” which implements minimum levels of control which are presumed to meet water quality standards.

On August 9, 2004, the KVWPCA submitted an LTCP to the PADEP utilizing the “demonstration approach” in which an attempt was made to demonstrate that existing CSO discharges did not adversely affect water quality and did not cause water quality standards to be exceeded in the Kiskiminetas River. In a letter dated January 29, 2008, PADEP disapproved the submitted LTCP and suggested that KVWPCA use the “presumption approach” and demonstrate in a revised LTCP either that the CSO discharges were limited to four (4) untreated overflows per year, or that the Authority would commit to providing full biological treatment of at least eighty-five percent (85%) of all combined sewer annual wet weather flows. The DEP also required the revised LTCP to include a plan to adequately convey and appropriately treat the annual wet weather flow from the combined portions of the sewage collection system and fully treat all sanitary sewer flows from separate sewers (sanitary sewage and storm water conveyed in separate pipes) during wet weather events. The KVWPCA submitted a revised LTCP on April 7, 2008 and the PADEP provided approval of the plan in a May 22, 2008 letter which also included a schedule for implementation of the plan.

As required by the LTCP, comprehensive monitoring for twelve (12) municipalities (Washington Township conducted their own) was conducted from September 1, 2008 through February 28, 2009. The results of this study (including flow monitoring) were presented in a report (Flow Monitoring and Modeling Study – “Flow Study”) dated August 2009. The Flow Study identified the volumes of base flow (dry weather flow consisting of sanitary wastewater and ground water infiltration) and peak flow (wet weather flow including base flow and storm water inflow) contributed by each Municipality. The Flow Study concluded that the KVWPCA’s conveyance facilities are adequate to meet the EPA CSO Control Policy standard of treatment of at least eighty-five percent (85%) of all combined sewer annual wet weather flows and to meet the PADEP peak core flow design standard (100% of flow from separate sewer systems plus 350% of base flow from combined sewer systems). The Flow Study also concluded, however, that the KVWPCA’s sewage treatment plant did not have adequate capacity to meet PADEP peak core standards for treatment.

Upon review of the Flow Study, the KVWPCA Board of Directors authorized their Engineer to develop and evaluate options to upgrade the sewage treatment plant and to analyze the cost of the options to ensure compliance with PADEP sewage treatment standards. A Basis of Design Report was completed and presented to the Board in January 2010. The Design Report recommended installing new Sequencing Batch Reactors (SBRs) and related upgrades to provide for treatment of peak core flows, and to incorporate biological nutrient removal capabilities into the proposed upgrades to meet anticipated discharge limits for nitrogen and phosphorus. The upgraded sewage treatment plant would need a hydraulic capacity with a design average daily flow of 7.0 MGD and a peak instantaneous flow of 31.0 MGD. The Design Report provided a cost estimate of $27,850,000 for the plant upgrades.

To fund the sewage treatment plant and system upgrades necessary to comply with PADEP treatment standards, the KVWPCA issued $32,390,000 in bonds (Net Interest Rate = 4.172%; Yield = 4.097%) on September 28, 2010 to provide funds to pay off several loans, fund the Debt Service Reserve Fund, construct the sewage treatment plant upgrades and to pay the costs for issuing the bonds. KVWPCA revenues will be used to satisfy the payment obligations on the bonds.

At a special meeting of the KVWPCA Board on September 22, 2010, a rate increase was approved to finance the bond issue with nine (9) Municipalities voting for the rate increase and four (4) Municipalities voting against the increase. The rate adopted by the Board consists of two parts: a non-flow based component and a flow-based component.

Three elements comprise the non-flow based component of the rate:

  1. A uniform flat rate of $1.55 per Equivalent Dwelling Unit (EDU) per month for payment of two existing loans from the Pennsylvania Infrastructure Investment Authority (PENNVEST).
  2. A uniform flat rate of $0.72 per EDU per month for payments of the three loans that are paid in full with the proceeds from the bond issue, and
  3. A uniform flat rate of $4.70 per EDU per month for the non-flow related costs of the sewage treatment plant upgrade.

Two elements comprise the flow based component of the rate:

  1. A flow volume credit for the existing surge capacity of the sewage treatment plant, and
  2. A flat rate per gallon of excess flow.

The flow-volume credit is determined by allocating the existing surge capacity of the sewage treatment plant proportionally on a flow-volume basis.

The existing surge capacity of the sewage treatment plant was determined using the data from the Flow Study and represents the difference between the total base flow (sewage plus groundwater, comprising dry weather flow) of 3.854 million gallons per day (MGD) and the peak flow, as determined by PADEP design criteria (350% of the base flow), to be 13.5 MGD. This is the amount of flow the sewage treatment plant can currently accommodate before causing a CSO. Each Municipality was credited a volume of 350% of its base flow in the determination of its excess flow.

Excess flow was determined for each Municipality by subtracting its flow volume credit from its peak flow (as determined by the Flow Study). Excess flow represents the amount of wastewater originating in a specific Municipality that is causing flow to the sewage treatment plant to exceed the plant’s treatment capacity, and thereby causing the need for the sewage treatment plant upgrades to reduce CSOs in compliance with the LTCP and the NPDES Permit.

An example of the Debt Service Calculation for a Municipality of the KVWPCA is as follows:

Debt Service Calculation – 2010 Bond (Debt per EDU):

Municipality A

Base Flow = 1.093 MGD

Peak Flow = 19.937 MGD

Equivalent Dwelling Units (EDUs):      2685

Flow-Volume Credit = (1.093 x 3.5) = 3.8255 MGD

Excess Flow = (19.937 – 3.8255) = 16.1115 MGD

Total Plant Excess Flow = 37.302 MGD

Municipality A % of Excess Flow = 16.1115/37.302 x 100 = 43.19%

Plant Total Flow Debt Service Per Month = $82,600

Municipality A Portion of Flow Debt Service Per Month = (.4319 x 82,600) = $35,677.11

Municipality A Flow Debt Service Per Month Per EDU = $35,677.11/2685 EDUs = $13.29

Non-Flow Debt Service Per Month Per EDU = $1.55 + $0.72 + $4.70 = $6.97

TOTAL Debt Service Per Month Per EDU = $13.29 + $6.97 = $20.26 (2010 Bond Issue)

An additional bond issue was required to cover costs associated with higher than anticipated construction costs, a pump station force main replacement project and post construction flow monitoring required by the PADEP permit. A separate bond was issued on May 28, 2014 for $4,800,000 (Net Interest Rate = 4.250%; Yield = 4.320%) to cover these costs.

An example Debt Service Calculation for this additional debt (2014 Bond) is as follows:

Municipality A

Municipality A % of Excess Flow = 43.19% (same as above)

Plant Total Debt Service Per Month related to 2014 Bond Issue: $18,700.00

Total Non-Flow Based Allocation Per Month: (53%) = $18,700 x .53 = $9,911

Total Flow Based Allocation Per Month: (47%) = $18,700 x .47 = $8,789

Municipality A Portion of Non-Flow Debt Service per Month Per EDU (Identical cost for all municipalities): $9,911/13,900 Total EDUs = $0.71/EDU  

Municipality A Portion of Flow Debt Service Per Month = (.4319 x $8,789) = $3,795.97

Municipality A Flow Debt Service Per Month per EDU = $3,795.97/2685 EDUs = $1.41

TOTAL Debt Service Per Month Per EDU = $1.41 + $0.71 = $2.12 (2014 Bond Issue)

TOTAL Combined Debt Service Per Month Per EDU = $20.26 + $2.12 = $22.38

The LTCP includes a requirement for post-construction flow monitoring to replicate the pre-construction flow monitoring conducted for the Flow Study. The KVWPCA will adjust the rate assessed to each Municipality for the Flow Debt Service based on the results of the post-construction flow monitoring.

1361 School Rd
Leechburg, PA 15656
Phone: (724)568-3655
Fax: (724)568-3554



FACIILITY IS CLOSED
TO PUBLIC ACCESS
PAYMENTS CAN BE
MADE BY PHONE
DURING THE FOLLOWING HOURS
8:00 am to 4:00 pm,
Monday thru Friday.
CLOSED WEEKENDS.

ONLINE BILL PAY
billpaybutton2a


paperless bill art2a1


Pay-by-Phone is available by calling (844) 254-0067.
You will need the following during your call:
    Account number
    Billing zip code
    Credit card

Click here for physical payment locations.

Go to top